In this article, you will learn:

What is the Scheduled Vs Actual Report?

This report shows a breakdown of the hours worked per day, allowing you to see the difference between the hours an employee worked and hours they were scheduled to work.
​

How to generate the Scheduled Vs Actual report?

  1. Navigate to the schedule

  2. Click on the blue Actions button

  3. Select Export CSV

  4. Select Scheduled VS Actual

  5. From the dropdown, choose which schedule you want to include

  6. Press the Save as CSV button

NB: To get a report that shows extra hours worked by each staff member, use the Timecard Analysis report.